Bellefield Area Sewer Projects

Bellevue Utilities is constructing three sewer improvement projects in the Bellefield area that began in April 2015 and will continue through Spring 2017. These improvements are needed to increase sewer capacity to meet growth demands and to replace aging infrastructure.

alerts iconSign up to receive emails or texts when there are updates for one of these projects

Sewer work to impact westbound SE 8th Street

Sewer main replacement work by Bellevue Utilities will close the curb lane of westbound Southeast Eighth Street from 114th Avenue Southeast to 112th Avenue Southeast starting May 26 until October.

The improvements are needed to increase sewer capacity for the Wilburton area as it continues to grow and to replace aging infrastructure.

The public can expect the following traffic impacts:                                

  • Access to local businesses will be maintained.
  • All traffic movements will be maintained; however expect traffic delays with the lane reduction on westbound Southeast Eighth Street
  • The pedestrian and bike paths along the north curb lane will be closed.

As part of the sewer improvements along Southeast Eighth Street, construction crews will also begin installation of support pilings and shoring for the sewer pipe in early June. This will generate some noise.

Learn more with this construction map.

SPRING 2015 –  SPRING 2016

Bellefield Pump Station Capacity Improvements. Replacing existing pump station at 112th Avenue SE and SE 15th Street with larger station and discharge pipe to meet growth in downtown Bellevue/East Central Business District. Project will affect traffic on 112th Avenue from SE 15th Street south to Bellevue Way. Questions? Please contact Jay Hummel at 425-452-4160 or jhummel@bellevuewa.gov

SUMMER 2015 – 
WINTER 2016

East Central Business District Sewer Trunkline Improvements. Replacing existing primary sewer pipes with larger pipes to meet growth in downtown Bellevue. Project will affect traffic on 112th Avenue SE from SE 15th Street north to SE 6th Street for about six months (September-early 2016). 112th will be reduced to one lane each direction within work zone. Intersection of 112th and 8th will be modified to reduce and/or prohibit turns to and from 112th during this time, but north/south traffic will be maintained. Questions? Please contact Jay Hummel at 425-452-4160 or jhummel@bellevuewa.gov

FALL 2015 –  SPRING 2017

Wilburton Sewer Capacity Improvements. Replacing sewer main with larger pipes to meet growth in Wilburton area. Work will begin in October starting at the north end of the project on the east side of I-405. Traffic restrictions will occur on westbound SE 8th Street with one lane closure, and on 114th Avenue SE, a partial and complete closure between Main Street and SE 8th Street for four months from March to July. Questions? Please contact Brandon Cole at 425-452-4474 or bcole@bellevuewa.gov